Planning permission

Do you need planning permission for a loft conversion or dormer?

Covers
loft conversion, dormer, rear dormer, hip to gable, L-shaped dormer, loft extension, attic conversion
The law
GPDO 2015, Schedule 2, Part 1, Class B, paragraphs B.1 to B.4
Applies to
England

Short answer

Often not, in England. A loft conversion that enlarges the roof, with a dormer or a hip-to-gable change, is permitted development under Class B of Part 1 of the General Permitted Development Order 2015 if it adds no more than 40 cubic metres to the original roof space of a terraced house, or 50 cubic metres on any other house. Every earlier addition to the roof counts towards that total. Nothing may rise above the highest part of the roof, or go beyond the plane of a front roof slope that faces a road.

Class B does not apply at all on Article 2(3) land, which includes conservation areas, National Landscapes and National Parks. There, a loft conversion that only adds rooflights can still be permitted development under Class C.

Check your own project Check your address

Development is not permitted by Class B if ... the cubic content of the resulting roof space would exceed the cubic content of the original roof space by more than (i) 40 cubic metres in the case of a terrace house, or (ii) 50 cubic metres in any other case

GPDO 2015, Schedule 2, Part 1, paragraph B.1(d)

The limits

  • Volume. "Resulting roof space" takes account of any enlargement to the original roof space, "whether permitted by this Class or not" (B.3). Cubic content is measured externally (article 2(1)). An end-of-terrace house is a terrace house for this purpose (paragraph I).
  • Height and front. No part higher than the highest part of the existing roof, and nothing beyond the plane of a roof slope that forms the principal elevation and fronts a highway (B.1(b), B.1(c)).
  • Exclusions. No veranda, balcony or raised platform, and no chimney, flue or soil and vent pipe under Class B (B.1(e)). Pipes and flues fall under Class G.
  • Materials. Similar in appearance to the house (B.2(a)). The technical guidance accepts felt, lead or zinc on a dormer's flat roof.
  • Eaves and set-back. The original eaves stay or are reinstated, and the dormer sits at least 0.2 metres from the eaves, measured along the slope, so far as practicable (B.2(b)(i)). Nothing extends beyond the outside face of an external wall of the original house (B.2(b)(ii)).
  • Side windows. Obscure-glazed, and non-opening unless the opening part is more than 1.7 metres above the floor (B.2(c)).

A hip-to-gable enlargement is exempt from the eaves and set-back rules. An enlargement that joins the original roof to the roof of a rear or side extension, such as an L-shaped dormer over an outrigger, is exempt from all of B.2(b). Class B is not available to flats, or once a house has been extended upwards under Class AA (B.1(h)).

Class B loft conversion limits Section, not to scale added volume no higher than the highest part of the existing roof front slope facing a highway: nothing beyond its plane 0.2 m min along the slope eaves maintained Added volume, counting earlier roof additions: 40 m³ terrace house, 50 m³ other houses

A worked example of the volume

A semi-detached house with a hipped roof. Measured externally, the roof is 7.2 metres front to back and the ridge is 3.0 metres above the eaves.

  • Hip to gable. The new gable is a triangle 7.2 metres wide and 3.0 metres high: 10.8 square metres. With the hip at the same pitch as the main roof, it runs back 3.6 metres to the end of the ridge, so the added space is a pyramid: 10.8 × 3.6 ÷ 3 = 12.96 cubic metres.
  • Rear dormer. 5.0 metres wide, with a face 2.4 metres high above the old slope. At this pitch the flat top meets the old slope 2.88 metres further back, so the added space is a wedge: 5.0 × 2.4 × 2.88 ÷ 2 = 17.28 cubic metres.
  • Total. 30.24 cubic metres, inside the 50 cubic metre limit for a semi-detached house.

If a previous owner had already added 20 cubic metres to the roof, with or without planning permission, the total would be 50.24 cubic metres. The whole conversion would then need planning permission, although the new work adds only 30.24.

What this means for you

Find out what the roof looked like when the house was built, or on 1 July 1948 if older, and measure every change since. Put the figures into the permitted development checker. Building Regulations approval is required to turn a loft into living space (Planning Portal), and work to a party wall may need notice under the Party Wall etc. Act 1996 (do you need a party wall agreement).

Getting certainty

A volume calculation within a cubic metre or two of the limit is exactly what a lawful development certificate settles. Send the council the calculation with the drawings. From 1 April 2026 the fee for householder works is £274, and the council has 8 weeks to decide.

Parallel ArchitectureLaw checked 29 September 2026How we write these guides

Sources

  1. GPDO 2015, Schedule 2, Part 1, Class B legislation.gov.uk
  2. GPDO 2015, article 2, interpretation legislation.gov.uk
  3. Permitted development rights for householders: technical guidance, September 2019 gov.uk
  4. Planning Portal: loft conversion, planning permission planningportal.co.uk
  5. Planning Portal: is Building Regulations approval needed for a loft conversion? planningportal.co.uk