Does the Party Wall Act apply to your work, and which notices do you need?

Whether the Party Wall Act applies, which notices you need, how much notice each needs, and the dates to serve them by.

What work is proposed?

You are the building owner, the Act's term for the owner carrying out the work. Tick all that apply.

Why this matters
A party wall is a wall shared with a neighbouring building. A party structure is a party wall, floor or other structure shared between buildings. A party fence wall is a garden wall standing astride the boundary, not part of a building. The line of junction is the boundary line between the two properties. A new wall at the line of junction comes under section 1 of the Party Wall etc. Act 1996, work to a party structure or a party fence wall under section 2, and adjacent excavation under section 6. The government's guide says minor work, such as plastering, wiring, sockets and drilling for shelves, needs no notice.
Where will the new wall stand in relation to the line of junction?

The line of junction is the boundary line between the two properties.

Why this matters
Astride the line, the new wall is a party wall if it is part of a building, or a party fence wall if it is not, such as a garden wall. The adjoining owner can consent to a wall astride the line within 14 days; without consent it must stand wholly on your land. Foundations that reach under the adjoining owner's land are what the Act calls projecting footings and foundations (the Party Wall etc. Act 1996, section 1(2) to (6)).
What work is proposed to the party structure?

A party structure is a party wall, floor or other structure shared between buildings. Tick all that apply.

Why this matters
Each is a right the Act gives the building owner, in section 2 of the Party Wall etc. Act 1996: to underpin, thicken or raise (2(2)(a)), to demolish and rebuild (2(2)(b) and (e)), to cut into (2(2)(f)), to cut away a projection (2(2)(g)), to cut in a flashing (2(2)(j)) and to expose (2(2)(n)). The same section covers a party fence wall. Each needs a party structure notice at least two months before the work begins (section 3(1) and (2)(a)).
How far is the excavation from the neighbouring building or structure?

Measure from the nearest part of the excavation to the nearest part of their building or structure.

Why this matters
Adjacent excavation is digging near a neighbour's building or structure, which can be a garden wall or an outbuilding. Within 3 m, the Act applies if the excavation goes lower than the bottom of their foundations (the Party Wall etc. Act 1996, section 6(1)). The owner of every building or structure within the distances is an adjoining owner for this section (section 6(4)).
How deep will the excavation go?

To the bottom of the new foundations, trench or basement.

Why this matters
Within 6 m, the Act applies if the excavation meets a line drawn down at 45 degrees from the bottom of their foundations, at the face of their wall (the Party Wall etc. Act 1996, section 6(2)). On level ground that line is as far below their foundations as it is from their wall.
How deep are the neighbouring foundations, if known?

Leave this blank if not known. A trial hole, dug beside their wall, or their original drawings can show it.

Why this matters
Both tests measure from the bottom of the neighbouring foundations (the Party Wall etc. Act 1996, section 6(1) and (2)). Without their depth the checker cannot say whether section 6 applies, so it treats the Act as applying until a trial hole shows otherwise. It assumes the ground is level between the two buildings.
Who are the adjoining owners?

The adjoining owner is the Act's term for the neighbouring owner affected by the work. Tick all that apply.

Why this matters
Every adjoining owner must be served, and the Act's meaning of owner is wider than the freeholder: anyone receiving, or entitled to receive, rent or profits from the property; anyone in possession of it, other than a mortgage lender, a tenant from year to year or for a shorter term, or a tenant at will; and a buyer under a contract to buy, or under an agreement for a lease, other than a tenancy from year to year or shorter (the Party Wall etc. Act 1996, section 20). In a building of flats there may be several owners on each side: the freeholder, and each leaseholder whose flat is next to the work.
When do you plan to start the work?

Optional. Enter a date as dd/mm/yyyy and the checker works out the latest date to serve each notice.

Why this matters
Serving a notice means giving it in a way the Act allows: in person, by post, or by email if the owner has agreed to that (the Party Wall etc. Act 1996, section 15). Each period runs from the day the notice is served, and a posted notice counts as served when it would arrive in the normal course of post (Interpretation Act 1978, section 7).

About this tool

Tick the work you plan and answer a few questions. The checker tells you whether the Party Wall Act appears to apply, which notices you need to serve, the minimum notice for each, the latest date to serve them for your start date, and what happens if the adjoining owner does not reply. The Act, the Party Wall etc. Act 1996, applies in England and Wales; this checker is written for England.

Jurisdiction
England
Law checked
29 September 2026
Tool version
1.1

Made and maintained by Parallel Architecture, a director-led architectural design practice working from Bristol and Brighton. Each rule is checked against the legislation itself and cited where it is applied. How we write the guides and tools.

General guidance on the law in England from the answers you enter, not advice on your project. Website terms.

What this checker is doing

It follows the law on party walls and on adjacent excavation, section by section, in the order the questions arise: the Party Wall etc. Act 1996.

  1. Does the Act cover the work? Three kinds of work are covered. A new wall at the line of junction, the boundary line between the two properties, where nothing is built at the line, or only a boundary wall that is not a party fence wall or the outside wall of a building (section 1). Work to an existing party structure, a wall or floor shared between buildings, or to a party fence wall, a garden wall astride the boundary, including underpinning, thickening or raising it (section 2(2)(a)), demolishing and rebuilding it (section 2(2)(b) and (e)), cutting into it (section 2(2)(f)), cutting away a chimney breast or other projection (section 2(2)(g)) and cutting in a flashing, the waterproof strip at a joint (section 2(2)(j)). Adjacent excavation, digging near a neighbouring building or structure (section 6). Minor work such as plastering, wiring, sockets and drilling for shelves is not on the list, and the government's guide says it needs no notice.
  2. The 3 metre and 6 metre tests. An excavation within 3 m of any part of the neighbouring building or structure, measured horizontally, is covered if any part of it within those 3 m goes lower than the bottom of their foundations (section 6(1)). Within 6 m, an excavation is covered if any part of it meets a line drawn down at 45 degrees towards it from the bottom of their foundations at the face of their wall (section 6(2)). On level ground that line is as far below their foundations as it is from their wall: with foundations 1 m deep, an excavation 4 m away is caught if it goes 5 m deep or more. The owner of every building or structure within those distances is an adjoining owner for these rules, not only the owner next door (section 6(4)).
  3. The minimum notice. A line of junction notice, for a new wall at the line of junction: at least one month before the work starts (section 1(2) and (5)). A party structure notice, for work to a party structure: at least two months before (section 3(2)(a)), or sooner if the adjoining owners and occupiers consent in writing (section 3(3)(a)). A notice of adjacent excavation: at least one month before (section 6(5)). An adjoining owner served with a party structure notice has one month to reply asking for extra work, in what the Act calls a counter notice (section 4(2)(b)).
  4. If the adjoining owner does not reply. It depends on the notice. For a wall astride the line of junction, if the adjoining owner does not consent within 14 days, you may build it only wholly on your own land, at your own expense. That is not a dispute (section 1(4)). For a party structure notice or a notice of adjacent excavation, no consent within 14 days is treated as a dispute, which is called a deemed dispute, and party wall surveyors are appointed: one agreed surveyor for both owners, or one for each owner, and those two select a third. The surveyors settle the dispute by an award (sections 5, 6(7) and 10).
  5. When a notice lapses. A party structure notice or a notice of adjacent excavation stops having effect if the work has not begun within 12 months, starting on the day it is served, and is not carried on without delay (sections 3(2)(b) and 6(8)). A line of junction notice has no such rule of its own, but the right to place projecting footings and foundations under the adjoining owner's land runs from one month to twelve months after the notice (section 1(6)).
  6. Who is served, and how. Serve every adjoining owner, as the Act defines owner: anyone receiving, or entitled to receive, rent or profits from the property; anyone in possession of it, other than a mortgage lender, a tenant from year to year or for a shorter term, or a tenant at will; and a buyer under a contract to buy, or under an agreement for a lease, other than a tenancy from year to year or shorter (section 20). Hand the notice to them in person; post it to their usual or last known home or place of business in the United Kingdom; for a company, send it to its secretary or clerk at its registered or main office; email it only if they have said they will accept notices that way, to the address they gave; or address it to "the owner" of the named property and hand it to someone there or, if nobody is there, fix it somewhere easily seen on the property (section 15). A posted notice counts as served when it would arrive in the normal course of post (Interpretation Act 1978, section 7).
  7. A common error. The government's guide says notice must be given between 2 months and a year before work starts. That is right only for a party structure notice (section 3). A line of junction notice, or a notice of adjacent excavation, needs one month (sections 1 and 6), and the 12 months is a rule about when a party structure notice or a notice of adjacent excavation lapses, not a window for serving it (sections 3 and 6).
  8. Why there is no notice generator here. Notices fail on the facts, not the wording: a missed owner, a leaseholder nobody checked for, a notice sent to the wrong address, or a notice of adjacent excavation without the plans and sections the Act requires (section 6(6)). The government publishes an explanatory booklet and example letters. Parallel does not act as a party wall surveyor.

Key rules

The Party Wall etc. Act 1996 covers three kinds of work: a new wall at the line of junction (section 1), work to a party structure (section 2), and adjacent excavation near a neighbouring building or structure (section 6). The building owner is the owner who wants to carry out the work; the adjoining owner is the neighbouring owner affected by it.

  • A line of junction notice must be served at least one month before work starts on a new wall at the line of junction, the boundary line between two properties (Party Wall etc. Act 1996, section 1(2) and (5)).
  • A party structure notice must normally be served at least two months before work to a party structure begins (section 3(2)(a)). A party structure is a party wall, floor or other structure shared between buildings.
  • With the written consent of the adjoining owners and occupiers, work to a party structure can start before the two months are up (section 3(3)(a)).
  • A notice of adjacent excavation must be served at least one month before the excavation starts (section 6(5)), with plans and sections showing the site and depth of the excavation (section 6(6)).
  • Within 3 metres of a neighbouring building or structure, measured horizontally, section 6 applies if any part of the excavation goes lower than the bottom of its foundations (section 6(1)).
  • Within 6 metres, section 6 applies if the excavation meets a line drawn down at 45 degrees from the bottom of the neighbouring foundations (section 6(2)). On level ground, with foundations 1 metre deep, an excavation 4 metres away is caught at 5 metres deep or more.
  • The owner of any building or structure within those distances is an adjoining owner for section 6, not only the owner next door (section 6(4)).
  • Every adjoining owner must be served. The Act's meaning of owner includes a freeholder entitled to rent, a tenant in possession under a tenancy longer than from year to year, and a buyer under a contract to buy (section 20).
  • If an adjoining owner does not consent in writing within 14 days of a party structure notice or a notice of adjacent excavation, a dispute is deemed to have arisen (sections 5 and 6(7)).
  • A dispute under the Act is settled by party wall surveyors: one agreed surveyor, or a surveyor appointed by each owner, and those two select a third. The surveyors settle the matters in dispute by an award (section 10).
  • Silence on a line of junction notice for a wall astride the line is not a dispute: without consent within 14 days, the wall may be built only wholly on the building owner's land, at the building owner's expense (section 1(4)).
  • A party structure notice or a notice of adjacent excavation stops having effect if the work has not begun within 12 months, beginning with the day of service, and is not carried on without delay (sections 3(2)(b) and 6(8)).
  • An adjoining owner served with a party structure notice has one month to serve a counter notice asking for extra works for their own use (section 4).
  • The two month period applies only to a party structure notice. A line of junction notice and a notice of adjacent excavation need one month (sections 1 and 6).
  • Minor work, such as plastering, wiring, sockets and drilling for shelves, needs no notice, the government's guide says.