Planning and permitted development

How much do householder planning applications cost, and how long do they take?

Short answer

In England, from 1 April 2026, a householder planning application for one house costs £548. Prior approval for a larger rear extension or an extra storey costs £249. A lawful development certificate for proposed householder work costs £274. Listed building consent has no fee.

The council has 8 weeks to decide a householder application, a lawful development certificate or a listed building consent, counted from receipt of a valid application. A larger rear extension can go ahead if the council has not responded within 42 days. Pre-application advice is not set by law: each council sets its own charge.

Fees from 1 April 2026

National fees are set by the Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits) (England) Regulations 2012. Since 1 April 2025 they rise each 1 April by the September consumer prices index, capped at 10% (regulation 18A). The September 2025 figure was 3.8%.

ApplicationFee
Householder application, one house (extensions, loft conversions, other alterations)£548
Householder application, two or more houses£1,083
Outbuildings, walls, fences and gates at a house£272
Prior approval: larger rear extension (Part 1, Class A) or extra storeys (Class AA)£249
Prior approval: solar panels on a flat roof on article 2(3) land (Part 14, Class A)£249
Lawful development certificate, proposed householder works£274 (half the application fee)
Lawful development certificate, existing worksThe full application fee
Discharge of conditions, householder£89
Removal or variation of a condition, householder£89
Non-material amendment, householder£46
Listed building consentNo fee
Certificate of lawfulness of proposed works to a listed buildingNo fee
Planning permission to demolish a building in a conservation areaNo fee
Works to protected trees or trees in a conservation areaNo fee
Householder appealNo fee

Since 6 December 2023 there is no free resubmission after a refusal or withdrawal: regulation 9, which gave one, was revoked. See planning refused: what next.

How long the council has

ApplicationPeriodWhere the rule is
Householder application8 weeksDevelopment Management Procedure Order 2015, article 34(2)(b)
Lawful development certificate8 weeksArticle 39(10)
Listed building consent8 weeksListed Buildings Regulations 1990, regulation 3(6)
Prior approval, larger rear extension42 days, then work may start if no responseGPDO 2015, Schedule 2, Part 1, paragraph A.4(10)(c)
Prior approval, extra storeysNo deemed approval: work may not start until approval is given in writingParagraph AA.3(13)

Each period runs only from receipt of a valid application: the right forms, plans, certificates, anything on the council's published local list, and the fee (article 34(4)).

Extensions of time, and the refund

A council may ask you to agree a longer period. Article 34(2)(c) allows "such extended period as may be agreed in writing". If you do not agree and no decision arrives in time, you can appeal against non-determination within 6 months of the end of the period.

If a householder application is not decided within 16 weeks and you have not agreed an extension or appealed, the council must refund the fee (regulation 9A).

A worked example

A householder application is received, valid and paid, on Monday 2 November 2026.

  • The 8 weeks begin on Tuesday 3 November and end on Monday 28 December 2026.
  • The 16 weeks for the refund end on Monday 22 February 2027.
  • The fee is £548. Under the draft regulations below, an application made on or after 8 December 2026 would pay £575 instead, so submitting a complete application before that date would matter if the draft is approved.

Pre-application advice

Councils charge for advice under section 93 of the Local Government Act 2003, and set their own prices. Two examples, as published on 28 September 2026:

CouncilHouseholder adviceNotes
Bristol City Council£520 including VAT, written advice with no meetingListed building advice £260, or £520 with a site visit; reply within 30 working days
Brighton and Hove City Council£154.50 for a written response; £237.16 with a site meeting£408.54 to £860.15 for listed buildings and conservation areas, where agreed necessary

See pre-application advice for what you get.

Proposed: changes from 8 December 2026

The draft would set the householder fee at £575 (£1,130 for two or more houses), outbuildings and boundary work at £285, and householder prior approval at £310. A lawful development certificate for proposed work would stay at half the application fee. Annual indexing would restart from 1 April 2027. Applications made before the commencement date would pay the old fees.

What this means for you

Budget the council's fee alongside drawings and any specialist reports, and submit a complete application: the clock does not start until it is valid. The planning permission route finder shows which application your project needs.

Parallel ArchitectureLaw checked 29 September 2026How we write these guides

Sources

  1. Planning Portal: application fees in England from 1 April 2026 planningportal.co.uk
  2. Fees for planning applications in England from 1 April 2026 (annual indexation) gov.uk
  3. Fees Regulations 2012, regulations 9A, 11, 14 and 18A legislation.gov.uk
  4. Fees (Amendment) Regulations 2023, SI 2023/1197, regulation 5 (revocation of regulation 9) legislation.gov.uk
  5. Development Management Procedure Order 2015, articles 34 and 39 legislation.gov.uk
  6. Planning (Listed Buildings and Conservation Areas) Regulations 1990, regulation 3, as substituted for England by SI 2008/551 legislation.gov.uk
  7. GPDO 2015, Schedule 2, Part 1 (paragraphs A.4 and AA.3) legislation.gov.uk
  8. Draft Fees (Amendment and Transitional Provision) Regulations 2026 legislation.gov.uk
  9. Planning practice guidance: before submitting an application, paragraph 004 gov.uk
  10. Planning Inspectorate: procedural guide for appeals on applications dated on or after 1 April 2026, section 4 gov.uk
  11. Bristol City Council: pre-application advice charging schedule 2026 to 2027 bristol.gov.uk
  12. Brighton and Hove City Council: household pre-application advice service brighton-hove.gov.uk

Where next