Costs and value

How much contingency should you allow on a home project?

Short answer

A contingency is money held back for costs that cannot be known when the budget is set: what is behind a wall or under a floor, the ground, and design detail that is not yet settled. It is not for upgrades you choose along the way.

Published guidance for homeowners starts at 10%. The Federation of Master Builders (23 February 2026) suggests at least 10% of the total project cost, and 15% or more for older homes or structural alterations. HomeBuilding (5 June 2020) suggests 10% on most sites and 20% on a sloping site, on bad ground or where there is a basement. The RICS cost planning standard, NRM 1, recommends that the allowance is assessed for the project's own risks, not set as a standard percentage.

The published guidance

These are national published figures from the sources named, with their dates.

SourceDateGuidance
Federation of Master Builders, How to budget for a renovation23 February 2026At least 10% of the total project cost; 15% or more for older homes or structural alterations
HomeBuilding, 15 ways to make sure you stay on budget5 June 202010% usually sufficient on most sites; 20% on a sloping site, bad ground or with a basement
RICS, NRM 1, 3rd editionEffective 1 December 2021Separate allowances for each category of risk, based on an assessment of the project, not a standard percentage

The two homeowner guides agree on the floor and on the direction: the less you know about the building and the ground, the more you hold back.

Why older and period buildings carry more risk

NRM 1 lists typical causes of construction risk. Many of them are the ordinary condition of an old house: existing buildings and adjacent structures, asbestos and other hazardous materials, ground conditions and ground water, existing services of unknown condition and location, and people living in the building during the work. The FMB's guidance names the same things in plainer terms: hidden structural problems, outdated wiring and drainage that only show once work begins.

A new extension on open ground has fewer of these. A renovation of a Victorian terrace, where floors come up and walls are opened, has most of them. That is why both homeowner guides move the figure up for older homes.

Design development risk and construction contingency

NRM 1 splits risk into four allowances, and the difference between the first two matters on a home project.

AllowanceWhat it coversWhen it should be used up
Design development riskDesign decisions not yet made, planning requirements, estimating data, provisional sums that give no price certaintyDuring the design process
Construction riskWhat is found on site: ground, existing structure, services, access, weatherDuring the build
Client change riskChanges you make to the scope, quality or programmeWhenever you make them
Client other riskYour own risks, such as funding or a date you must be in byAs they arise

An early estimate needs all four. Once a contractor's price is agreed on complete information, the design development allowance should have been absorbed into the design, and what remains is the construction contingency you hold during the build. Your own changes of mind are not unforeseen. Budget for them separately, or accept that they come out of the same pot. NRM 1 recommends that transfers into and out of the risk allowances are recorded at each stage, so you can see where the money went.

How the allowance comes down

NRM 1 says the risk allowance at the earliest stages can be a significant percentage of the estimate, and that it falls to zero once all accounts are settled. The way to bring it down is information. NRM 1 names more detailed design and further site investigation as ways to reduce risk. On a house that means a measured survey, an early view from a structural engineer, opening up where the structure is uncertain, trial pits where the foundations matter, and an asbestos survey before anything is disturbed.

What this means for you

Hold the contingency as a separate line, outside the contractor's price, and outside the figure you tell yourself the project costs. Decide in advance who can authorise spending it and how it will be recorded. If the contingency is not needed, it is money you still have; if it was never there, the project stops or the finish suffers. The rest of the budget structure is in what a cost plan contains.

Our own figures from recent projects will be added here.

Parallel ArchitectureLaw checked 29 September 2026How we write these guides

Sources

  1. RICS: NRM 1, Order of cost estimating and cost planning for capital building works, 3rd edition, sections 2.15 and 3.4 and group element 13 rics.org
  2. Federation of Master Builders: How to budget for a renovation and avoid going over budget, 23 February 2026 fmb.org.uk
  3. HomeBuilding: 15 ways to make sure you stay on budget, 5 June 2020 homebuilding.co.uk