Costs and value

What does a cost plan for a home project contain?

Short answer

A cost plan is a structured estimate of what a project will cost, prepared before any contractor has priced it. The RICS standard for it, NRM 1, divides the total into separate parts: facilitating works, the building works, the main contractor's preliminaries, overheads and profit, project and design team fees, other project costs, risk allowances and inflation. VAT is assessed separately, and the report must say what is included and what is left out.

At the start it is an order of cost estimate: a floor area multiplied by a cost per square metre, with the other parts added. As the design develops it becomes an elemental cost plan, priced element by element. Neither is a tender. A tender is a contractor's offer to carry out defined work for a price.

The parts, in the order NRM 1 builds them

NRM 1 (3rd edition, effective from 1 December 2021) sets out the constituents of an order of cost estimate as a running sum. On a home project they come out like this.

PartWhat it covers on a house extension or renovation
Facilitating worksWork needed before building can start: demolition, removal of asbestos or other hazardous materials
Building worksThe new and altered building, by element: substructure, frame and walls, roof, windows and doors, stairs, internal finishes, fittings, services, work to the existing building, external works and drainage
Main contractor's preliminariesThe cost of running the site: management, scaffolding, welfare, temporary protection, skips
Main contractor's overheads and profitThe contractor's business costs and margin
Project and design team feesDesign, structural engineering, surveys, the principal designer roles, cost advice
Other project costsCosts that are part of the project but not the works or fees, for example planning fees, party wall costs, insurances and the cost of moving out during the works
Risk allowancesDesign development risks, construction risks, client change risks and other client risks, each assessed separately
InflationTender inflation to the date tenders come back, then construction inflation to the mid-point of the build
VAT assessmentShown separately. NRM 1 recommends VAT is excluded from the estimate and that specialist advice is taken on the rates

The sum of the first six parts is what NRM 1 calls the base cost estimate, and it carries no allowance for risk or inflation. Risk and inflation are added on top to reach the cost limit. Keeping them visible stops them being buried in the rates, where nobody can see them being spent.

Exclusions are part of the plan

NRM 1 section 2.19 says items included or excluded should be clearly communicated to the client, and lists a statement of inclusions and exclusions among the contents of the report. On a home project, check where these sit: loose furniture, appliances, landscaping beyond the immediate works, finance costs, and anything that depends on surveys not yet done. An exclusion is not a saving. It is a cost you will meet from another budget, so it needs a line of its own in your own figures.

Order of cost estimate, cost plan and tender

These three are often called "the price". They are different things, produced at different times with different information.

Order of cost estimateElemental cost planTender
WhenBefore design, or at the start of itAs the design developsOnce the construction information is complete
BasisFloor area times a cost per m2, plus the other partsQuantities measured from drawings, priced per elementThe contractor's own pricing of the drawings, specification and schedule of works
Who produces itThe cost consultant or design teamThe cost consultant or design teamEach contractor invited to price
What it is forTesting whether the project is affordable and setting a cost limitKeeping the design inside the cost limitChoosing a contractor and fixing the contract sum

NRM 1 places the order of cost estimate at stages 0 and 1 of the RIBA Plan of Work 2020, and formal cost plans at stages 2, 3 and 4. Each formal cost plan develops the previous one, and changes should be reconciled and explained, including any transfers into or out of the risk allowances. The tender then tests the plan against the market. How to run that step is in how to tender building work.

Why a good estimate gives a range

Early in a project much of what drives cost is still unknown: the ground, the condition of the existing structure, the level of finish you will choose, and the market at the date of tender. NRM 1 says the risk allowance at the earliest stages can be a significant percentage of the estimate, falling to zero once the accounts are settled. It also recommends that risk allowances are assessed for the project, not applied as a standard percentage.

The RICS professional standard on cost prediction (1st edition, effective from 1 July 2021) says that "initially, ranges should be used". A single figure at concept stage suggests a certainty that does not exist. A range, with a statement of what would move the figure up or down, tells you more: where the uncertainty sits and what would narrow it, such as a measured survey, a structural engineer's early view or a trial pit.

How much to hold back for the unknowns is covered in contingency. The fees that sit inside the plan are set out in design and professional fees, and the VAT treatment in VAT on building work.

What this means for you

Ask for the estimate in this structure, with the exclusions listed and the risk and inflation allowances shown as separate lines. Check the date the rates were current (NRM 1 calls it the estimate base date) and how inflation was carried forward from it. Treat the low end of any range as the figure that only holds if nothing goes wrong.

Parallel ArchitectureLaw checked 29 September 2026How we write these guides

Sources

  1. RICS: NRM 1, Order of cost estimating and cost planning for capital building works, 3rd edition, sections 2.4, 2.15 to 2.19 and 3.4 rics.org
  2. RICS: Cost prediction, professional standard, 1st edition, section 2.1 rics.org
  3. RICS: Quantity surveyor services, England and Wales, May 2022 rics.org