Tendering and contracts

What does a contract administrator do?

Short answer

A contract administrator runs the building contract for the client. Under JCT's Minor Works Building Contract that means issuing instructions and variations, valuing the work and certifying payments, deciding extensions of time, certifying practical completion, managing the rectification period and issuing the final certificate. Several of those decisions have to be made fairly between client and contractor, even though the client appoints and pays the contract administrator.

JCT's HO/B has no contract administrator. HO/C, Minor Works, Intermediate and the Standard Building Contract all have one. A homeowner does not have to appoint one, but without one the decisions fall to you.

The role and the title

The role is not protected. Anyone competent may administer a building contract. JCT's forms name the role by a title that depends on who holds it; JCT's practice note lists the alternatives. One of those titles is protected by statute: only a person on the statutory register may practise or carry on business under it (1997 c. 22, section 20(1)). Anyone else who holds the role is the contract administrator. The same section also provides that it does not affect the validity of a building contract in customary form.

What the contract administrator does under Minor Works

JCT publishes a pack of model administration forms for MW 2024 and MWD 2024. The list of forms is a fair summary of the job:

StageWhat the contract administrator doesJCT model form
Before the contractMakes sure the contract particulars are complete: dates, liquidated damages, rectification period, interim valuation dates, retention percentages, insurance
During the workIssues instructions in writing, including variations to the workInstruction
DelayDecides whether the contractor should have more time. Minor Works allows extensions for delay beyond the contractor's controlExtension of Time
Late finishCertifies that the contractor has not finished by the completion date; the client may then deduct liquidated damages at the rate in the particularsNon-completion; Notice of Intention to Deduct Liquidated Damages
PaymentValues the work at each interim valuation date and certifies what is dueValuation; Interim Certificate
Paying lessWhere the client intends to pay less than the sum due, the notice that says soPay Less Notice
CompletionCertifies practical completionPractical Completion Certificate
AfterwardsLists defects in the rectification period and certifies when they have been made goodCertificate of Making Good
The endSettles the final account and certifies the final sumFinal Certificate

JCT's practice note says its contracts, apart from the Home Owner forms, take account of the Construction Act. Under Minor Works the interim certificate states what is due, and a pay less notice is needed to pay less: the machinery of sections 110A and 111 of the Housing Grants, Construction and Regeneration Act 1996. On a home you live in, the Act itself does not apply (section 106), but the contract still does. See payment and retention for homeowners.

Two things make the job harder than the list suggests. JCT's comparison table shows that Minor Works has no detailed rules for valuing variations, so each change needs a clear instruction and a price agreed or fairly assessed against the priced documents. And the practical completion certificate triggers several things at once, covered in practical completion and the rectification period.

Acting fairly between the parties

The contract administrator is the client's agent when giving instructions. For valuations, certificates and extensions of time, the job is different. JCT's practice note describes the traditional role as an independent contract administrator. NBS's review of the RIBA Building Contracts 2018 notes situations where the contract administrator is required to act impartially, and warns that getting this wrong can make the work cost more, finish later and end in dispute.

In practice, that means an extension of time is granted if the contract says the contractor is entitled to it, whether or not the client wants the building sooner. RICS makes the same point from the other side: the person certifying practical completion should not owe duties to the contractor, which can happen where designers are novated to a design and build contractor.

Which contracts have one

ContractContract administrator?
JCT HO/B 2021No. You deal with the contractor directly
JCT HO/C 2021Yes. A consultant you appoint under the HO/CA consultancy agreement
JCT MW 2024 and MWD 2024Yes
JCT IC 2024 and ICD 2024Yes, with a quantity surveyor
JCT SBC 2024Yes, with a quantity surveyor
JCT DB 2024No independent administrator. You act, or appoint an agent
RIBA Domestic Building Contract 2018Yes. The client can take the role, which the guidance advises only in limited cases, such as very simple work

Does a homeowner need one?

No law requires it. JCT's HO/B exists for homeowners who deal with the builder directly, and JCT's practice note suggests consultants on small domestic jobs might recommend it where they provide only part of a service.

What you give up without one is a person who checks the work before each payment, prices changes, and decides delay and completion on the contract's terms. If you plan to pay against valuations, expect changes, or are living in the house during the work, those are the decisions you would otherwise make yourself.

How fees are charged

Contract administration can be charged as a percentage of the construction cost, as a fixed fee, or by time. JCT's HO/CA consultancy agreement has a section for the consultant's services and fees. We have not found a current, published survey of contract administration fees on their own, so we do not quote a figure. See design and professional fees for the wider picture.

What this means for you

If your project is more than a straightforward job with one builder and a fixed price, the contract administrator's decisions on payment, changes, delay and completion are where money is won or lost. Decide at the start whether someone will make them for you.

Parallel Architecture administers building contracts on projects it has designed and on others where the design is complete: see tender and contract administration.

Parallel ArchitectureLaw checked 29 September 2026How we write these guides

Sources

  1. JCT, MW and MWD 2024 Admin: contract administration model forms jctltd.co.uk
  2. JCT, MW 2024 User Checklist jctltd.co.uk
  3. JCT, Deciding on the appropriate JCT contract 2024 (practice note, June 2025), paragraphs 9, 30, 52, 53 and 73, and Part 4 jctltd.co.uk
  4. JCT, HO/C and HO/CA 2021 jctltd.co.uk
  5. NBS: RIBA Building Contracts 2018, what's new (13 April 2018) thenbs.com
  6. RICS, Defects and rectifications, 2nd edition (August 2024), section 3.1.2 rics.org
  7. Housing Grants, Construction and Regeneration Act 1996, sections 106, 110A and 111 legislation.gov.uk
  8. 1997 c. 22, section 20: use of the protected title legislation.gov.uk