Tendering and contracts
Paying a builder: stage payments, retention and your rights
Short answer
If you live in the home, or intend to, and the contract is mainly for work on it, Part II of the Housing Grants, Construction and Regeneration Act 1996 does not apply (section 106). There are no statutory stage payments, payment or pay less notices, suspension rights or adjudication.
Your contract can include all of those, and JCT's Minor Works contract does. Whatever the contract says, the Consumer Rights Act 2015 requires a builder who is a trader to work with reasonable care and skill (section 49), and gives you the right to have poor work done again or the price reduced (sections 54 to 56).
(1) This Part does not apply ... (a) to a construction contract with a residential occupier (see below) ... (2) A construction contract with a residential occupier means a construction contract which principally relates to operations on a dwelling which one of the parties to the contract occupies, or intends to occupy, as his residence.
What the Act would otherwise give
| Section | The statutory rule | On your own home |
|---|---|---|
| 108 | Either party can refer a dispute to adjudication at any time | Only if the contract provides it. JCT's Home Owner forms do |
| 109 | Payment by instalments, unless the work is to last less than 45 days | Only if the contract provides it |
| 110A | A payment notice no later than five days after each payment due date | Only if the contract provides it |
| 111 | Pay the notified sum unless a pay less notice is given in time | Only if the contract provides it |
| 112 | The payee may suspend work on at least seven days' notice if not paid | No statutory right |
| 113 | Pay when paid clauses are ineffective, except on insolvency | No statutory rule |
Who counts as a residential occupier
Two consequences follow from the wording of section 106(2):
- Landlords are outside it. Work on a house you let and do not live in is not work for a residential occupier, so the Act applies to the contract in full.
- The definition of a dwelling is narrow. A "dwelling-house" in this section does not include a building containing a flat. For work on a whole building divided into flats, the exclusion turns on whether the work principally relates to the flat you live in.
What the contracts put in its place
- JCT HO/B and HO/C 2021. A lump sum including VAT, paid in one sum on completion or in agreed instalments. JCT's practice note says these forms include adjudication although the Act does not require it.
- JCT Home Repair and Maintenance Contract. Payment only on completion, which is why JCT says the work should not run beyond four weeks.
- JCT MW 2024. Interim valuations and certificates, a pay less notice and a retention. JCT says its contracts, other than the Home Owner forms, take account of the Construction Act.
- RIBA Domestic Building Contract 2018. NBS's review of the 2018 edition notes that it includes payment provisions similar to the Act's, although the Act does not apply to residential occupiers.
- FMB domestic contracts. A standard version, and a version with a defects stage payment or retention to cover snagging and remedial work.
Stage payments and deposits
Citizens Advice's advice for England is to pay in stages, so problems can be put right before the final payment, with the payment points agreed in advance. On deposits it says:
- avoid paying everything up front, and offer to buy materials yourself instead of paying a deposit for them;
- if a deposit cannot be avoided on a long job, do not agree to more than 25%;
- check whether the deposit is insured, or held by an escrow company registered with the Financial Conduct Authority;
- pay by card; a credit card payment of between £100.01 and £30,000 may give a section 75 claim against the card provider.
Tie each stage to finished work (roof on, first fix complete), not to a date.
Retention
Retention is a percentage of each payment held back as security against defects. Under JCT MW 2024 the contract particulars state the percentage of the value certified before practical completion and the percentage on and after it (clause 4.4). The difference is the retention. JCT's comparison table notes that Minor Works does not hold it in trust.
For example, on a £60,000 contract with 95% certified before practical completion and 97.5% after, you hold £3,000 until practical completion and £1,500 until the defects are made good. RICS calls that second half the contractor's most immediate incentive to come back. See practical completion and the rectification period.
Your rights under the Consumer Rights Act 2015
Chapter 4 of Part 1 applies to a trader supplying a service to a consumer (section 48). What the builder told you is binding where you relied on it (section 50), and where no price or time was agreed, the price and time must be reasonable (sections 51 and 52).
Every contract to supply a service is to be treated as including a term that the trader must perform the service with reasonable care and skill.
If the work falls short, you can require the builder to do it again, within a reasonable time, without significant inconvenience to you and at its own cost (section 55). If that is impossible, or the builder does not do it in that way, you can require a price reduction, up to the full price, refunded within 14 days of the builder agreeing you are entitled to it (section 56). Damages and the other ordinary remedies remain (section 54(6) and (7)), and no contract term can exclude liability for reasonable care and skill (section 57(1)).
What this means for you
Because the statutory payment rules do not protect either side on your own home, the contract has to. Agree the payment points, how each payment is checked, what is held back and when it is released, before work starts. JCT's Home Owner forms, MW 2024 and the RIBA Domestic Building Contract all give you a framework to do that. See which building contract.
Parallel Architecture values the work and certifies payments as contract administrator: see tender and contract administration.
Sources
- Housing Grants, Construction and Regeneration Act 1996, sections 104 to 113 legislation.gov.uk
- Consumer Rights Act 2015, Part 1, Chapter 4 (sections 48 to 57) legislation.gov.uk
- JCT, Deciding on the appropriate JCT contract 2024 (practice note, June 2025), paragraphs 33, 49 to 55 and Part 4 jctltd.co.uk
- JCT, MW 2024 User Checklist jctltd.co.uk
- JCT, MW and MWD 2024 Admin: contract administration model forms jctltd.co.uk
- NBS: RIBA Building Contracts 2018, what's new (13 April 2018) thenbs.com
- FMB domestic building contracts fmb.org.uk
- Citizens Advice: before you get work done on your home (England) citizensadvice.org.uk